We have not been updating the blog. It has been quite depressing to visit building site as well.
The last few weeks have been even more depressing watching other houses (we have been watching on the homeone forum ) started around the same time as ours and they have reached lock up. Good for them.
Bricking started on 9 January 2009. At the end of 6 weeks all we had completed was the garage bricking. But the target to finish bricking the whole house was 6-9 weeks .
Whole of Feb and 3 weeks of March - we saw plumbing and gas connection done but no bricking.
Finally on a positive note :- now things are happening again with a bang. Hope it continues.
Once they started the brick work last Wednesday it has been going good. Downstairs, back and the 2 side are complete but for the area around the windows.
In the front there has been a tiny bit of bricking. Starting to look real nice. We are so much happier with these brickies - Not so shoddy as the previous one - seem more organised, neat and fast. In 4 working days they have done most of the downstairs bricking . So guess something good came out of the waiting.
So here are some photos of our bricking
On a more cherful - we are thrilled of our brick and window colours.
BAck of the house - Can see the alfresco pillars
Right side of the house - Big opening is the roller door for the garage
Kitchen Window/Alfresco
Alfresco / Home Theatre (Left Side of the house)
Study / Home Theatre (Left Side of the house)
Garage